Brightwave makes connecting your new development simple with our streamlined process. Follow these steps to get your project connected.

SUBMIT YOUR DEVELOPMENT
Kick things off by lodging your development details with us. We’ll assess your project, confirm eligibility, and provide preliminary infrastructure advice.
RECEIVE YOUR INFRASTRUCTURE AGREEMENT
Once we’ve reviewed your site, we’ll issue a Telecommunications Infrastructure Agreement tailored to your development. This covers scope, timing, technical requirements and costs.


LOCK IN YOUR BUILD WITH CONDITIONAL APPROVAL
After signing the agreement and paying applicable charges, you’ll receive a Letter of Conditional Approval — often required for planning approval or construction finance.
DESIGN YOUR FIBRE PATHWAYS
Your civil designer or engineer will prepare pit and pipe designs in line with Brightwave specifications. We provide detailed design guidelines to support your consultants.


CONSTRUCT AND CERTIFY YOUR BUILD
Once your design is approved, your contractor installs the conduit and pit infrastructure. On completion, submit As Built drawings for certification.
BRIGHTWAVE BUILDS AND CONNECTS
With certified civil works in place, Brightwave installs the fibre network, terminates equipment, and conducts final testing. The site is now officially Ready for Service.


PROVISIONING AND CONNECTION
We issue your Letter of Provision confirming the site is serviceable. You can now advise residents, tenants or purchasers that high-speed Brightwave fibre is available.